Pier 26 G3 Track and Grading

PROJECT OVERVIEW

Project Name: Pier 26 G3 Track and Grading
Project Owner: Hamilton Port Authority
Project Consultant: Stantec
Project Type: Stipulated Price Contract
Project Value: $ 2.7 million
Status: Completed in 2016
Location: Hamilton, ON

 

PROJECT HIGHLIGHTS

Construction of 5 new train layover lines, and integrated a new spur line through an existing facility while it remained fully operational.

 